Richey Street Phase II

Planning and design work for Phase II of Richey Street that covers between Southmore Avenue and South Houston Blvd has been completed. Engineering is complete and construction is slated to commence May 2022. $60K were allotted for the planning and design phase of this project.

 

Project Details

Project Name: Richey Phase 2

Location: Richey Street between Southmore Avenue and South Houston Blvd.

Budget: $2.9M

Partners: City of Pasadena

Consultants/Contractors: Mainlane Industries

Expected Date of Completion: Q2 2024

Contact Information: Rick Guerrero, Executive Director, RGuerrero@PasadenaEDC.com